Page 1 of 1

DCS showing wrong campaign status

Posted: Fri 07 Dec 2007 6:04 am
by CN_Vertex
Hi all,

Just after analyzed last mission, DCS shows active the "Build Next Mission" button. Two days after that, I've just opened it and it now shows active the "Analyze Last Mission" one. No change have been done in SEOW MP or DB.

Is ther a DB field that can be edited to change this status? DCS "thinks" that mission have been built, but thats not true.

Thanks!

Posted: Fri 07 Dec 2007 9:11 pm
by IV/JG7_4Shades
Hi Vertex,

Sometimes, when Analyze times are very long, the DCS tends to lose connection to the DB and the final status command is not issued. The table Sector_Status contains the status information. Here are a few lines from a recent successful campaign:

Code: Select all

2	Italy	Initialized	194209011200	Genova.mis	4
3	Italy	Built	194209011300	SE-Genova-194209011300.mis	1
4	Italy	Analyzed	194209011300	eventlog_SE-Genova-194209011300.lst	3
Cheers,
4Shades

Posted: Mon 10 Dec 2007 5:51 pm
by CN_Vertex
Thx 4Shades, I'll study these example to fix my seow's DB :wink:

Is there a DCS limit to close connection?, maybe I should try to elevate it to avoid this problem.

Thx again.

Posted: Mon 10 Dec 2007 8:41 pm
by IV/JG7_4Shades
No, the connection is closed by the MySQL server I think. The DCS will keep trying forever.

Cheers,
4Shades